UXO Area Clearance of SP MoD ‘Los Castillejos’ Proving Range

Contractor:
Client:
Release date:

Responsibility

Technical Director of the Consortium being responsible for project management and supervision
Bid and Hiring Preparation
Official interlocution with the Client (GIED)


Description

Project aimed at the Location, Disposal and Removal (Clearance) of Explosive Artifacts and Unexploded Ammunition (UXOs) scattered all over the proving range of 'Los Castillejos' (Tarragona).
The Project Information Management system generates demilitarization progress reports. The ultimate goal of the project is the Certification of the land as a demilitarized (cleared) zone and valid for its civil use.
The main figures of the project are:



  • Team of 18 people involved in the project implementation

  • Number of projectiles and UXOs disabled 420

  • 738.805m2 of cleared land (9 differentiated zones)